What should be done before starting demolition work?

Prepare for the Massachusetts 4G Hoisting License Test. Utilize interactive quizzes and multiple choice challenges designed to enhance your understanding. Gear up for success!

Before starting any demolition work, calling Dig Safe and disconnecting all utilities is a crucial step. This process ensures the safety of workers and the general public by preventing accidental damage to underground utilities such as gas, water, electricity, or telecommunications. By identifying and disconnecting these lines prior to demolition, potential hazards, such as explosions, electrocution, or water damage, are significantly minimized.

Additionally, this step is often mandated by law and is part of the proper regulatory framework governing construction and demolition activities. It ensures compliance with safety regulations, helping to ensure that all necessary precautions are taken before any physical work begins.

While confirming weather conditions, ensuring tool readiness, and obtaining permits are all important aspects of preparing for a demolition project, the safety of the site with respect to utilities takes precedence. Without securing the utilities, no amount of planning regarding the tools or permits can prevent serious accidents or injuries during the demolition process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy